PROJECT
REPORT FOR THE PROPOSED CONSTRUCTION
OF
SCHOOL, INDUSTRIAL TRAINING INSTITUTE.ORPHANAGEFOR
GNLC
|
|
| |
|
|
| |
The
detailed estimate for the proposed
construction of school, industrial
training institute, orphanage, boys
Hostel, girls Hostel, Employees Quarters,
Library, Swimming Pool, Guest House
and Community Hall.
|
|
| |
|
|
| 1. |
Land |
|
| |
|
|
| |
Land
to be selected with 50 acres, extent
value of land per acre is Rs.10 lakhs.
Total Cost of land is 5 crores. Land
has to be Completely covered with
6’0’’height Barbed
wire fencing with concrete post at
every 8’ centre to centre and
front side Random rubble masonry compound
will with 7’0 height to be constructed
with 15’0 wide main gate and
4’0 wide wicket gate. |
|
| |
|
|
| 2. |
School
Building |
|
| |
|
|
| |
In
ground floor, school building with
veranda, stair case to upper floor,
10 Class Rooms, Office Rooms, Head
Master Room, Boys Toilet and Girls
Toilet
In First floor 10 Class Rooms, One
Hall for Laboratory, Boys Toilet and
Girls Toilet to be constructed as
per Drawing School building constructed
with total Plinth area 10,000 Square
feet in ground and first floor
|
|
| |
|
|
| 3. |
Industrial
Training Institute |
|
| |
|
|
| |
INDUSTRIAL
TRAINING INSTITUTE constructed with
5 Class Room and Principal Room, Office
Room building in 2000 Square feet
area. Work Shop Constructed under
1000 Square feet each with 3 blocks.
Works Shop for Welding, Electrical
winding, AC Mechanic etc. industrial
training institute Constructed with
total area of 5000 Square feet with
4 Separate building
|
|
| |
|
|
| 4. |
Orphanage |
|
| |
|
|
| |
Orphanage
constructed in 5000 Square feet plinth
area in ground and first floor to
accommodate Orphanage Children. In
Ground Floor, Office Room, 4Halls
And Boys Toilet will be constructed.
In first floor Girls accommodate in
4 Halls and Girls Toilet with Stair
Case upper Floors.
|
|
| |
|
|
| 5. |
Boys
Hostel |
|
| |
|
|
| |
Boys
Hostel Constructed in 5000 Square
feet in 2 floor. In Ground floor 10
Rooms, with Stair Case to upper floors
and Toilet block. In first floor 10
Rooms With Stair Case to terrace floor
and Toilet block. A total number of
200 boys Accommodate |
|
| |
|
|
| 6. |
Girls
Hostel |
|
| |
|
|
| |
Girls
Hostel Constructed in 5000 Square
feet in 2 floors. In ground floor
10 Rooms, with Stair Case to upper
floors and Toilet block. In first
floor 10 Rooms With Stair Case and
Toilet block. A total number of 200
girls Accommodate in Hostel. |
|
| |
|
|
| 7. |
Kitchen
for the Hostel and Orphanage |
|
| |
|
|
| |
Kitchen
and Dining Hall Constructed with 5000
Square feet plinth area in Ground
floor. Kitchen, Store Room, Wash area.
Separate Dining Hall for Girls, Dining
Hall for Boys and Dining Hall for
Orphanage Children’s.
|
|
| |
|
|
| 8. |
Employee’s
Quarters |
|
| |
|
|
| |
Quarters
for employees to be Constructed in
Ground and two upper floors with total
built up area of 25000 Square feet.
Each Quarters have 400 Square feet
builtup area with one Hall, One Bed
Room With attached Toilet, One Kitchen
and common Stair Case to upper floors.
50 Families to be accommodated in
4 blocks. Of 12 family each and two
block of 13 family in each block.
|
|
| |
|
|
| 9. |
Library |
|
| |
|
|
| |
A
library Constructed in 1500 Square
feet in Ground floor and first floor
Library block consist of Librarian
room, a big Hall in each floor with
provision Of one toilet in each floor.
|
|
| |
|
|
| 10. |
Swimming
pool |
|
| |
|
|
| |
Swimming
pool Constructed in the 1000 Square
feet area. The Swimming pool depth
varies from 2’6’’to
7’6’’ depth. A Separate
Swimming pool for Children’s
to be Constructed. A Swimming pool
with provision of dress changing room.
Shower Room also Constructed. |
|
| |
|
|
| 11. |
Guest
house |
|
| |
|
|
| |
Guest
house Constructed with built up area
of 3000 Square feet in ground and first
floor. If ground
floor one hall, dining, kitchen and
2 bed rooms with attached toilet And
in first floor one hall, three bed
rooms with attached toilet and provision
For stair case in upper floors.
|
|
| |
|
|
| 12. |
Community
hall |
|
| |
|
|
| |
A
Community hall Constructed with 4000
Square feet in ground floor provision
for prayer meetings, ceremonies to
be conducted in this community hall. |
|
| |
|
|
| 13. |
Machinery
and vehicles |
|
| |
|
|
| |
Machinery
for , industrial training institute,
vehicles such as van 5 nos and 1 bus
for orphanage and 1 bus for school. |
|
| |
|
|
| 14. |
Furniture
and computers |
|
| |
|
|
| |
Computers
for school, Office and furniture for
school building to be purchased such
as table, benches, chairs, almirah etc. |
|
| |
|
|
| 15. |
Well
and overhead tank |
|
| |
|
|
| |
5
Nos 200 depth 6’’ dia
bore well and 5 nos over head tank
constructed to Fulfill requirement
of water.
|
|
| |
|
|
| |
PROJECT
SUMMARY |
|
| |
|
|
| |
Sl.
NO.
|
Description
of
Building |
Area |
Rate |
Unit |
Amount
Rs |
Amount
$ |
| |
|
|
|
|
|
|
| 1. |
Land |
50 |
10,00,000/- |
Acre |
5,00,00,000.00 |
1,255,335 $ |
| |
Land Registration |
50 |
80,000/- |
Acre |
40,00,000.00 |
100,426$ |
| |
Compound wall and
fencing |
LS |
|
|
12,00,000.00 |
30,128 $ |
| 2 |
School Building |
10,000 |
475/- |
Sqft |
47,50,000.00 |
119,256 $ |
| 3 |
Industrial training
Institute |
|
|
|
|
|
| a. |
class room building |
2000 |
475/- |
Sqft |
9,50,000.00 |
23,851 $ |
| b. |
Workshop Shed |
3000 |
400/- |
Sqft |
12,00,000.00 |
30,128 $ |
| 4. |
orphanage building |
5000 |
500/- |
Sqft |
25,00,000.00 |
62,766 $ |
| 5. |
Boys hostel |
5000 |
550/- |
Sqft |
27,50,000.00 |
69,043 $ |
| 6. |
Girls hostel |
5000 |
550/- |
Sqft |
27,50,000.00 |
69,043 $ |
| 7. |
Kitchen and
dinning
Hall |
5000 |
500/- |
Sqft |
25,00,000.00 |
62,766 $ |
| 8. |
Employee's quarters |
25000 |
575/- |
Sqft |
1,43,75,000.00 |
360,908 $ |
| 9. |
library hall |
1500 |
500/- |
Sqft |
7,50,000.00 |
18,830 $ |
| 10. |
Swimming pool |
LS |
|
|
10,00,000.00 |
25,106 $ |
| 11. |
Guest house |
3000 |
575/- |
Sqft |
17,25,000.00 |
43,309 $ |
| 12. |
Community hall |
4000 |
500/- |
Sqft |
20,00,000.00 |
50,213 $ |
| 13. |
Machinery |
LS |
|
|
70,00,000.00 |
175,746 $ |
| |
Van |
5 |
6,00,000/- |
Each |
30,00,000.00 |
75,320 $ |
| |
Bus |
2 |
10,00,000/- |
Each |
20,00,000.00 |
50,213 $ |
| 14. |
Furniture &
Computers |
|
|
|
40,00,000.00 |
100,426 $ |
| 15. |
Bore well with
motor |
5 |
1,00,000/- |
Each |
5,00,000.00 |
12,553 $ |
| |
Over head tank |
5 |
5,00,000/- |
Each |
25,00,000.00 |
62,766 $ |
| 16. |
Consulttants Fees,
TNEB charges,
Approval charges,
site development,
Road etc.., |
|
|
|
55,50,000.00 |
139,342 $ |
| |
|
|
|
|
|
|
| |
Totel |
|
|
|
11,70,00,000.00 |
2,937,484 $ |
|
|
| |
|
|
|
|
|
|
| |
|
|
|
|