  PROJECT REPORT FOR THE PROPOSED CONSTRUCTION OF
SCHOOL, INDUSTRIAL TRAINING INSTITUTE.ORPHANAGEFOR GNLC
 
     
 
The detailed estimate for the proposed construction of school, industrial training institute, orphanage, boys Hostel, girls Hostel, Employees Quarters, Library, Swimming Pool, Guest House and Community Hall.
 
     
1. Land  
     
 
Land to be selected with 50 acres, extent value of land per acre is Rs.10 lakhs. Total Cost of land is 5 crores. Land has to be Completely covered with 6’0’’height Barbed wire fencing with concrete post at every 8’ centre to centre and front side Random rubble masonry compound will with 7’0 height to be constructed with 15’0 wide main gate and 4’0 wide wicket gate.
 
     
2. School Building  
     
 
In ground floor, school building with veranda, stair case to upper floor, 10 Class Rooms, Office Rooms, Head Master Room, Boys Toilet and Girls Toilet

In First floor 10 Class Rooms, One Hall for Laboratory, Boys Toilet and Girls Toilet to be constructed as per Drawing School building constructed with total Plinth area 10,000 Square feet in ground and first floor
 
     
3. Industrial Training Institute  
     
 
INDUSTRIAL TRAINING INSTITUTE constructed with 5 Class Room and Principal Room, Office Room building in 2000 Square feet area. Work Shop Constructed under 1000 Square feet each with 3 blocks. Works Shop for Welding, Electrical winding, AC Mechanic etc. industrial training institute Constructed with total area of 5000 Square feet with 4 Separate building
 
     
4. Orphanage  
     
 
Orphanage constructed in 5000 Square feet plinth area in ground and first floor to accommodate Orphanage Children. In Ground Floor, Office Room, 4Halls And Boys Toilet will be constructed. In first floor Girls accommodate in 4 Halls and Girls Toilet with Stair Case upper Floors.
 
     
5. Boys Hostel  
     
 
Boys Hostel Constructed in 5000 Square feet in 2 floor. In Ground floor 10 Rooms, with Stair Case to upper floors and Toilet block. In first floor 10 Rooms With Stair Case to terrace floor and Toilet block. A total number of 200 boys Accommodate
 
     
6. Girls Hostel  
     
 
Girls Hostel Constructed in 5000 Square feet in 2 floors. In ground floor 10 Rooms, with Stair Case to upper floors and Toilet block. In first floor 10 Rooms With Stair Case and Toilet block. A total number of 200 girls Accommodate in Hostel.
 
     
7. Kitchen for the Hostel and Orphanage  
     
 
Kitchen and Dining Hall Constructed with 5000 Square feet plinth area in Ground floor. Kitchen, Store Room, Wash area. Separate Dining Hall for Girls, Dining Hall for Boys and Dining Hall for Orphanage Children’s.
 
     
8. Employee’s Quarters  
     
 
Quarters for employees to be Constructed in Ground and two upper floors with total built up area of 25000 Square feet.

Each Quarters have 400 Square feet builtup area with one Hall, One Bed Room With attached Toilet, One Kitchen and common Stair Case to upper floors. 50 Families to be accommodated in 4 blocks. Of 12 family each and two block of 13 family in each block.
 
     
9. Library  
     
 
A library Constructed in 1500 Square feet in Ground floor and first floor Library block consist of Librarian room, a big Hall in each floor with provision Of one toilet in each floor.
 
     
10. Swimming pool  
     
 
Swimming pool Constructed in the 1000 Square feet area. The Swimming pool depth varies from 2’6’’to 7’6’’ depth. A Separate Swimming pool for Children’s to be Constructed. A Swimming pool with provision of dress changing room. Shower Room also Constructed.
 
     
11. Guest house  
     
  Guest house Constructed with built up area of 3000 Square feet in ground and first floor.

If ground floor one hall, dining, kitchen and 2 bed rooms with attached toilet And in first floor one hall, three bed rooms with attached toilet and provision For stair case in upper floors.

 
     
12. Community hall  
     
 
A Community hall Constructed with 4000 Square feet in ground floor provision for prayer meetings, ceremonies to be conducted in this community hall.
 
     
13. Machinery and vehicles  
     
 
Machinery for , industrial training institute, vehicles such as van 5 nos and 1 bus for orphanage and 1 bus for school.
 
     
14. Furniture and computers  
     
  Computers for school, Office and furniture for school building to be purchased such as table, benches, chairs, almirah etc.  
     
15. Well and overhead tank  
     
 
5 Nos 200 depth 6’’ dia bore well and 5 nos over head tank constructed to Fulfill requirement of water.
 
 

 
  PROJECT SUMMARY  
     
 
Sl.
NO
.
Description of
Building
Area Rate Unit Amount Rs Amount $
             
1. Land 50 10,00,000/- Acre 5,00,00,000.00 1,255,335 $
  Land Registration 50 80,000/- Acre 40,00,000.00 100,426$
  Compound wall and fencing LS     12,00,000.00 30,128 $
2 School Building 10,000 475/- Sqft 47,50,000.00 119,256 $
3 Industrial training
Institute
         
a. class room building 2000 475/- Sqft 9,50,000.00 23,851 $
b. Workshop Shed 3000 400/- Sqft 12,00,000.00 30,128 $
4. orphanage building 5000 500/- Sqft 25,00,000.00 62,766 $
5. Boys hostel 5000 550/- Sqft 27,50,000.00 69,043 $
6. Girls hostel 5000 550/- Sqft 27,50,000.00 69,043 $
7.

Kitchen and dinning
Hall

5000 500/- Sqft 25,00,000.00 62,766 $
8. Employee's quarters 25000 575/- Sqft 1,43,75,000.00 360,908 $
9. library hall 1500 500/- Sqft 7,50,000.00 18,830 $
10. Swimming pool LS     10,00,000.00 25,106 $
11. Guest house 3000 575/- Sqft 17,25,000.00 43,309 $
12. Community hall 4000 500/- Sqft 20,00,000.00 50,213 $
13. Machinery LS     70,00,000.00 175,746 $
  Van 5 6,00,000/- Each 30,00,000.00 75,320 $
  Bus 2 10,00,000/- Each 20,00,000.00 50,213 $
14. Furniture & Computers       40,00,000.00 100,426 $
15. Bore well with motor 5 1,00,000/- Each 5,00,000.00 12,553 $
  Over head tank 5 5,00,000/- Each 25,00,000.00 62,766 $
16. Consulttants Fees,
TNEB charges,
Approval charges,
site development,
Road etc..,
      55,50,000.00 139,342 $
             
  Totel       11,70,00,000.00 2,937,484 $